City of Rome - New Police Facility

Project ID: 
2023 SPLOST
Project Type:
Capital Project
Project Status: 
Approved

New construction of building, parking, and maintenance shop for the Rome Police Department.

FINANCIALS - UPDATED 10.21.2025
ORIGINAL PROJECT BUDGET AMOUNT EXPENDED ON PROJECT TO DATE REMAINING FUNDS TO DATE PROJECTED COMPLETION DATE
$22,481,289 $5,548,862 16,932,427 2027

 

Status Updates

10.21.2025 - Land has been purchased at Riverside Parkway and Riverside Industrial with plans for future permanent home of Rome Police Department. Solicitation of architect is underway.

 

4.2024 - Open to the public at new location, 375 Technology Blvd.

3.2024 - Three (3) month build out completed. Department relocated to 375 Technology Blvd.

11.2023 - Building purchased at 375 Technology Blvd for temporary Rome Police Department headquarters.