City of Rome - New Police Facility
Project ID:
2023 SPLOST
Project Type:
Capital Project
Project Status:
Approved
New construction of building, parking, and maintenance shop for the Rome Police Department.
| ORIGINAL PROJECT BUDGET | AMOUNT EXPENDED ON PROJECT TO DATE | REMAINING FUNDS TO DATE | PROJECTED COMPLETION DATE |
|---|---|---|---|
| $22,481,289 | $5,548,862 | 16,932,427 | 2027 |
Status Updates
10.21.2025 - Land has been purchased at Riverside Parkway and Riverside Industrial with plans for future permanent home of Rome Police Department. Solicitation of architect is underway.
4.2024 - Open to the public at new location, 375 Technology Blvd.
3.2024 - Three (3) month build out completed. Department relocated to 375 Technology Blvd.
11.2023 - Building purchased at 375 Technology Blvd for temporary Rome Police Department headquarters.