2023 LMIG Paving List
|
Miles
|
| Cordle - COMPLETED |
0.3 |
| Lovell Street - COMPLETED |
0.3 |
| Split Branch Ct. - COMPLETED |
0.113 |
| Foliage Way - COMPLETED |
0.053 |
| Honeytree Trail - COMPLETED |
0.196 |
| Treehouse Trail - COMPLETED |
0.168 |
| Sapling Ct. - COMPLETED |
0.026 |
| Trillium Trail - COMPLETED |
0.541 |
| Redfern Trail - COMPLETED |
0.177 |
| Bob White Ct. - COMPLETED |
0.027 |
| Nan Lee Drive - COMPLETED |
0.28 |
| Beech Creek Drive - COMPLETED |
0.35 |
| Donley Drive - COMPLETED |
0.35 |
| Glendale - Rolled over to 2024 |
0.4 |
| Ave B Shannon - Rolled over to 2024 |
0.16 |
| Ave C Shannon - Rolled over to 2024 |
0.16 |
| 2nd Street Shannon - Rolled over to 2024 |
0.6 |
| 3rd Street Shannon - Rolled over to 2024 |
0.65 |
| Nottingham Way - COMPLETED |
0.17 |
| Nottingham Court - COMPLETED |
0.06 |
| Pembroke Way - COMPLETED |
0.115 |
| Doncaster Drive - COMPLETED |
0.51 |
| Barnesdale Way - COMPLETED |
0.27 |
| Lady Marion - COMPLETED |
0.4 |
| Juniper Street - COMPLETED |
0.28 |
| Norwood - Rolled over to 2024 |
0.15 |
| Henton - COMPLETED |
0.2 |
| Henson Road - COMPLETED |
1.5 |
| Angel Road - COMPLETED |
1.62 |
| Berryrun Drive - COMPLETED |
0.195 |
| Grandberry Ct. - COMPLETED |
0.104 |
| Bayberry Circle - COMPLETED |
0.055 |
| Songberry Ct. - COMPLETED |
0.053 |
| Twin Court - Rolled over to 2024 |
0.1 |
| Margo Trail - Rolled over to 2024 |
1.2 |
Total LMIG Paved = 8.413 mi. (71% completed)
|
11.833
|
| |
|
County Paving / SPLOST
|
|
| South end of Terhune - Rolled over to 2024 |
0.6 |
| Wax Old Rockmart to 101 - Rolled over to 2024 |
0.37 |
| Old Dalton Road (140 - 156) - COMPLETED |
4 |
| East Hermitage - COMPLETED |
3.835 |
| Morrison Campground (Gentry - 293) - COMPLETED |
1.951 |
| Blacks Bluff (Brushy to State Line) - COMPLETED |
3.34 |
| Padlock - County - COMPLETED |
0.4 |
| Padlock - City - COMPLETED |
1.4 |
| Wax Road S of Plemones - Rolled over to 2024 |
3.25 |
| Jake Whorton Road - Rolled over to 2024 |
2.1 |
Total County / SPLOST Paved = 14.926 mi. / 70% completed
|
21.246
|
| |
|
Carryover
|
|
| Biddy Road - Rolled over to 2024 |
1.55 |
| Trentwood - COMPLETED |
0.62 |
Total Carryover Completed 2023 = 0.62 mi. (40% completed)
|
1.55
|
| |
|
TOTAL PAVING COMPLETED 2023 = 23.959 mi. (68% completed)
|
35.249
|