| 2022 LMIG Paving List | Miles | Completed | 
| Ward Mountain Road - COMPLETED | 1.25 | 1.25 | 
| Payne Road - COMPLETED | 0.25 | 0.25 | 
| Woods Road - COMPLETED | 2.1 | 2.1 | 
| Industrial Blvd. - COMPLETED | 0.73 | 0.73 | 
| Calhoun Road - COMPLETED | 2.75 | 2.75 | 
| Blacks Bluff Road - COMPLETED | 4.8 | 4.8 | 
| Bryan Springs - COMPLETED | 0.174 | 0.174 | 
| Highlander Trail - COMPLETED | 0.78 | 0.78 | 
| Biddy Road - (Rollover) | 1.55 |  | 
| Total Miles | 14.384 | 12.834 | 
| County Funds |  |  | 
| Payne Avenue - COMPLETED | 0.056 | 0.056 | 
| Nan Ellen - COMPLETED | 0.114 | 0.114 | 
| Mardi Way - COMPLETED | 0.06 | 0.06 | 
| Cardinal Drive - COMPLETED | 0.1 | 0.1 | 
| Goodman Road - COMPLETED | 0.195 | 0.195 | 
| Total Miles | 0.525 | 0.525 | 
| 2021 LMIG Carryover |  |  | 
| N. 2nd Street (Lindale) - COMPLETED | 0.15 | 0.15 | 
| N. 4th Street (Lindale) - COMPLETED | 0.1 | 0.1 | 
| Avenue D (Lindale) - COMPLETED | 0.3 | 0.3 | 
| Avenue C (Lindale) - COMPLETED | 0.3 | 0.3 | 
| Trentwood - COMPLETED | 0.62 | 0.62 | 
| Carrington Place - COMPLETED | 0.13 | 0.13 | 
| Lionel Court - COMPLETED | 0.085 | 0.085 | 
| Lionel Lane - COMPLETED | 0.31 | 0.31 | 
| Friar Tuck Road - COMPLETED | 0.435 | 0.435 | 
| Little John Circle - COMPLETED | 0.2 | 0.2 | 
| Scarlett Lane - COMPLETED | 0.05 | 0.05 | 
| Total Miles | 2.68 | 2.68 | 
| SPLOST |  |  | 
| Old Dalton Road - COMPLETED | 4 | 4 | 
| Trent Drive - COMPLETED | 0.177 | 0.177 | 
| Total Miles | 4.177 |   | 
| Total Paving | 21.766 | 20.216 (updated 2.6.2024) | 
| Total Percent Paved = 93% |  |   |